- Project Overview
Royal Columbian Hospital Parkade Membrane Removal
Lorem Ipsum has been the industry's standard dummy text ever since 1966, when designers at Letraset and James Mosley the librarian at St Bride Printing Library in London, took a 1914 Cicero translation and scrambled it to make dummy text for Letraset's Body Type sheets. It has survived not only many decades, but also the leap into electronic typesetting, remaining essentially unchanged. It was popularised thanks to these sheets and more recently with desktop publishing software like Aldus PageMaker and Microsoft Word including versions of Lorem Ipsum.
- The Client's Needs
What The Client Needed From Us
- Keep the parkade open No full closures — the deck had to keep serving emergency and staff parking through the entire scope.
- Protect air quality Adjacent to occupied hospital space, so silica dust and fumes had to be contained at source.
- Hit the warranty spec: The new membrane's warranty required a certified SSPC/CSP profile — no shortcuts on prep.
- Predictable schedule Work sequenced around hospital operations with firm level-by-level handovers.

- The Starting Point
The Condition We Inherited
The existing PMMA traffic membrane had delaminated across large sections, trapping moisture and cracking at the joints. Previous patch repairs had left inconsistent thicknesses and multiple coating layers bonded to the slab.
Core samples showed variable substrate soundness and areas of laitance that would fail any adhesion test if coated over. There was no clean plane to work from — every zone had to be assessed before a removal method was assigned.
- Project Challenges
The Challenges We Solved From Us
- Live, occupied environmentZero tolerance for dust migration into a functioning hospital and its ventilation intakes.
- Mixed coating layersSeveral bonded systems of differing hardness meant no single removal technique covered the whole deck.
- Overnight-only access Productive work compressed into short night windows with full clean-up before day traffic returned.
- Slab-to-drain tolerances Profile had to be achieved without altering deck slope or damaging drains and expansion joints.
A zoned, multi-method removal plan — each area matched to the right technique, all captured at source by dust-shrouded equipment.
Rather than force one tool across the whole deck, PDB mapped the parkade into removal zones. Sound areas went to shrouded diamond grinding; heavier build-up and joints were addressed with shot blasting; edges and detail work were hand-ground. Every pass fed HEPA-filtered vacuum recovery, keeping the process effectively dustless.
This let us tune productivity to each condition, protect the surrounding hospital, and consistently land on the CSP 3 profile the membrane warranty demanded.
- Services & Methods
Services & Methods Deployed
01
Architectural Concrete Blasting
(Vancouver, Abbotsford) Controlled blasting methods that refine texture and reveal natural character while protecting the concrete’s strength.
02
Exposed Aggregate Finishing
03
Surface Preparation
04
Dust Containment
05
Edge & Detail Work
06
Profile Verification
A dedicated site supervisor coordinated directly with hospital facilities each shift — confirming zone access, ventilation isolation, and level handovers before any equipment ran.
- Commercial façades and entryways
- Exposed concrete walls and panels
- Decorative walkways and plazas
- Retail, institutional, and public spaces
- Custom architectural elements and precast components
- Project Process
The Process, Step By Step
01
Assessment & core sampling
Mapped substrate condition, coating layers, and moisture to define removal zones and set targets.
02
Containment set-up
Established barricading, ventilation isolation, and HEPA vacuum recovery before any removal began.
03
Zoned coating removal
Grinding, shot blasting, and hand-detail work applied by zone to strip to sound concrete.
04
Surface profiling
Refined the deck to a consistent CSP 3 profile without altering slope or damaging joints.
05
Verification & handover
Profile and adhesion confirmed, level cleaned, and returned to service the same night.

- The Final Result
The Outcome Delivered
A fully stripped, certified deck — handed back level by level with the hospital never losing full capacity.
The coating contractor received a substrate that passed adhesion testing on the first pass, protecting the membrane warranty. All work was completed inside the planned overnight windows with zero dust complaints from hospital operations.
- Project Management & Site Controls
The Approach We Recommended
The right method for each zone — not one tool forced across the whole deck — is what let us stay dustless and on schedule in a live hospital.
PDB Site Supervisor
Serving the Lower Mainland, and more
PDB provides architectural concrete finishing throughout Langley, Vancouver, Abbotsford, Burnaby, Delta, and surrounding areas.
From small decorative applications to large architectural concrete blasting projects, we deliver work that stands the test of time.
To learn more or request a consultation, contact PDB today.